This article series provides architects and engineers with prescriptive, actionable guidance for migrating a single workload from Amazon Web Services (AWS) to Azure. It covers the full migration life cycle, from planning and preparation through execution, evaluation, and the decommissioning of AWS resources.
This series focuses on workloads that range from simple to moderately complex and are mostly independent from other workloads in your organization. It doesn't cover mission-critical workloads.
Migrating a workload from AWS is a strategic initiative that requires careful planning and stakeholder alignment. Without a solid migration plan and proper preparation, you risk introducing unplanned disruptions, which can erode confidence in your workload.
Workload migration strategy
A like-for-like migration strategy minimizes risk and is typically the safest path to Azure. When you take this approach, the workload continues to use existing architecture and operational patterns. Migrations are most successful when they avoid scope creep, like paying existing technical debt or introducing optimizations during the workload hosting transition. The goal is that the migrated workload meets the same key performance indicators (KPIs) on Azure that it met on AWS. It should maintain the same service-level agreements (SLAs), service-level objectives (SLOs), and any bugs that currently exist in the workload.
Tip
Minimize changes during migration and focus on validating performance and stability. After you complete the migration, you can explore technical debt repayment and further optimizations.
Recommended tools
Use AWS and Azure tools where appropriate to augment your migration process. These tools support the following tasks:
- Upfront discovery
- Azure architecture planning based on data gathered about your AWS workload
- Data and compute platform transfer
- Post-migration validation
- Resource cleanup
Use Workload Discovery on AWS to assess your workload. You can combine AWS tooling with Azure tooling, like Azure Migrate, to assess AWS instances and provide sizing recommendations for Azure resources. Optionally, you can explore non-Microsoft solutions, like Dr Migrate or CAST Highlight, to assist with code analysis, dependency mapping, and migration readiness assessments.
Timeline assumptions
The migration of a workload can span several weeks or months. The duration depends on the complexity of the workload and your migration and cutover strategy. The following timeline shows a typical workload migration that uses a like-for-like approach for a moderately complex workload. A moderately complex workload typically includes multiple components and dependencies, but it's not mission-critical and doesn't integrate deeply with other systems.
Workload team responsibility
The team currently responsible for the workload in AWS is typically also responsible for the workload in Azure. This team should migrate the workload. Outsourcing the migration to talent outside of the workload team can lead to the following outcomes:
- Unexpected discoveries late in the process
- An undertrained workload team
- A reduced sense of ownership
In many cases, you can engage external partners who have Azure expertise to support migration. These partners include systems integrators and the Microsoft Industry Solutions Delivery team. They can lead planning and preparation, while the workload team carries out the production cutover by using partner-developed runbooks and automation.
Workload teams should consult with migration experts as part of the process, but the team should drive the process and remain closely involved.
Prerequisites
Before you plan the migration, ensure that you have the following prerequisites in place:
Prior experience: You need prior experience with core cloud concepts and AWS and a basic understanding of Azure services and cloud migration processes.
Stakeholder alignment: You need to share and agree on timelines, budget estimates, and project milestones with stakeholders to ensure that all parties align.
Support strategy: Purchase a Microsoft support plan and investigate options for free or community support.
Platform strategy: This series describes how to migrate a single workload. It assumes that your platform foundation is in place and that your migration strategy is defined and aligns with the Cloud Adoption Framework for Azure.
As part of this strategy, establish an existing platform landing zone. Your migrated workload becomes an application landing zone and is part of your organization's Azure landing zone topology. It exists under a management group hierarchy, connects to specific networks or remains isolated from them, and follows the required governance policies.
Investment in training or partner support: Assess your team's Azure skills and plan for training or partner support as needed.
You should also do a migration readiness assessment. This assessment scores your readiness to migrate across 10 dimensions. After the assessment, hold a kickoff workshop that includes all stakeholders to gather requirements and constraints and ensure buy-in.
To help you plan and successfully migrate your workload, proceed through the five phases in the following order:
Each phase includes detailed steps and checklists that guide you through the migration process.
Important
Throughout each phase, involve your operations team to address operational readiness. Their tasks include workload monitoring and alerting and the implementation of health dashboards. Plan a formal handoff so that the operations team is prepared to manage the workload in Azure. For example, you can set up Azure Monitor dashboards and alerts analogous to AWS CloudWatch after the migration completes.